AZ360 Project Update
View the online AZ360 project dashboard for current project status information. The project is GREEN and ON TRACK heading for Phase 1 implementation in May 2025.
Departmental UAT Begins Nov. 18
User Acceptance Testing (UAT) is crucial to confirming the AZ360 Project’s success. Departmental UAT, which runs Nov. 18-Feb. 7, 2025, allows agency testers to verify that the AZ360 processes and functions align with agency business requirements and meet the needs of end users in a real-world environment. Testers may also identify any process gaps and provide feedback for improvements.
Revised Interface Testing Schedule is Now Available
A revised Interface Testing schedule was recently posted on the Project website.
Agency Performance Appraisal Gap Planning Underway
Between Phase 1A and 1B implementation, (May 2025 through April 2026), the interface that currently maps information to the two State performance appraisal systems, MAP or AZ Performs, will not be available. ADOA’s Human Resources team is working directly with the agencies on alternative options.
Employee Action Needed - HRIS Data Cleansing
The project team is asking all employees to review their Y.E.S. data records and ensure that the information is current, complete and accurate. This is necessary to ensure testing and parallel payroll processing goes smoothly. Employees should keep Y.E.S. date current until AZ360 goes live in May 2025.